Milestones and estimates as ranges

Leading projects and incidents

Break the project into , and make each one something you can demo. "One customer can pay by card in " is a good milestone (staging is the test copy of ). " done" is not.

Demoable milestones expose integration problems, where the pieces fail to fit together, early, while they are still cheap to fix. Give estimates as ranges with a confidence, such as "four to six weeks, most likely five". Narrow the range as unknowns get answered.

A single date hides uncertainty, and people hear it as a promise. For work across teams, put the riskiest connection between teams in the first milestone, not the last.

Common trapmilestones split by team or layer: they all look green until the week everything has to connect, and then the whole project turns red at once.

A question to check yourself, an AI practice session and 1 cheat sheet entry come with the full roadmap. Unlock

Resources for this stage

Start with· follow one of these

  • BookFree
    Shape Up

    Ryan Singer, Basecamp · Intermediate

    Free book on shaping and scoping work so projects actually finish

  • BookFree
    Google Site Reliability Engineering Book

    Google · Advanced

    The chapters on managing incidents and blameless postmortem culture

Keep handy

Also worth your time

  • Why adding people to a late project makes it later, and other coordination costs

Mark this stage as not done?