Final Year Project Proposal Best Practices

Chapter 2 · Practice 4 of 4

Avoid scope that depends on data, hardware or people you do not control

From Scope the project to fit the calendar

Why it matters

Many projects stall for weeks waiting on something outside the team: a hospital that promised a dataset, a company API key that never arrives, sensors that have to be imported, a client who stops replying.

For every outside dependency, write down:

DependencyWho controls itDo we have it today?Fallback if it never arrives
Patient records datasetPartner hospitalNo, verbal promisePublic dataset or synthetic data
GPS hardware moduleMarket supplierOrderedPhone GPS for the demo

If a must feature depends on something you do not have yet, either get it before the proposal is approved or move that feature to the could group. Examiners often ask about data access; having the answer in writing is a strong signal of feasibility.

Do

  • List every outside dependency with a fallback
  • Secure critical data or hardware before approval

Avoid

  • A must feature that rests on a verbal promise